Barcelona have reached an agreement with Turkish construction company Limak to complete the Spotify Camp Nou renovation, removing the possibility of appointing a different contractor for the stadium’s final construction phase.
According to Mundo Deportivo, the agreement has been signed after investors deposited an additional €300 million in financing, approved by club members at the Ordinary General Assembly on September 19.
The agreement provides greater clarity over a project that has experienced delays, rising costs and tensions between Barcelona and Limak.
More importantly, it establishes a timetable for the stadium’s most complicated remaining operation: installing the roof through the 3,000-tonne structure known as the ‘Big Lift’.
Barcelona retain Limak despite previous tensions
Changing contractors had previously been considered as a possible alternative if disagreements over deadlines and execution could not be resolved.
Spotify Camp Nou, Barcelona stadium
Limak will complete the Spotify Camp Nou construction. (Photo by Alex Caparros/Getty Images)
However, Barcelona and Limak have now agreed on the final phase, with the construction company retaining responsibility while continuing to use subcontractors where necessary.
The financial backing has also moved forward, as Barcelona’s assembly approved €510 million in additional financing, comprising €300 million specifically for stadium construction and €210 million through media notes to address cash-flow pressures caused by delays.
The club subsequently completed the €300 million financing operation on November 13.
The Big Lift will determine Barcelona’s return to Camp Nou
According to the signed agreement, the roof installation will begin immediately after the 2026-27 season and must be completed during the second half of 2027-28.
Barcelona have provisionally reserved the Estadi Olimpic Lluis Companys for the first half of that campaign, although the current expectation is to return to Camp Nou in early 2028.
Barcelona and Real Madrid players
Barcelona are expecting to return to Camp Nou in 2028. (Photo by David Ramos/Getty Images)
The club has also abandoned plans to reopen the Third Tier gradually because of evacuation requirements and difficulties obtaining municipal licences.
Instead, the entire section will become operational when Barcelona return following the temporary move to Montjuic.
Camp Nou’s commercial potential
Barcelona’s confidence in the project is supported by the revenue already being generated at the partially reopened stadium.
The latest league Clasico against Real Madrid produced €19.1 million in ticket revenue, despite an attendance of 62,055.
However, one record-breaking Clasico does not guarantee that the projected revenue will become sustainable, and the real test will be whether Barcelona can consistently monetise the expanded capacity, hospitality facilities and commercial spaces once construction is complete.